Did A Quest For Efficiencies Almost Sink PCU North Dakota?

by admin on April 18, 2014

130911-N-ZZ999-001It has been great to see Virginia Class sub builders race each other to drive down cost and schedule. But when these competitive pressures start to impact crew safety, we all need to step back, take a few deep breaths, and re-evaluate.

For the PCU North Dakota, the pressure to make schedule–and improve upon the Virginia Class build time record of 62 months–has been particularly acute. It was more than just a race for efficiencies. PCU North Dakota builders and designers were protecting future sub production–and their jobs–from Washington budget-cutters.

To a casual observer or Congressional policymaker, the North Dakota builders seemed to be doing pretty well. Throughout 2013, their performance helped keep the Virginia Class Submarine Program healthy, and won the Program a big new multi-year block buy–and a big slice of the Navy’s shrinking shipbuilding budget. But behind the scenes, the PCU North Dakota evidently suffered. And now, just a few days after the boat was set to embark upon Alpha Trials, the PCU North Dakota’s problems became public, with NAVSEA canceling the planned May Commissioning date, citing problems with the boat.

Media outlets are focused on the Commissioning delay. But that’s not the real story. The real story is that a stressed Program, facing performance and budget pressure, seems to have come darn close to sending an unready, unsafe boat to sea.

A race for efficiencies almost became a literal race to the bottom.

What Happened?

virginia_1News reports suggest that the Virginia Program is facing an unspecified set of design-related problems with the Flight III’s new bow (sporting the new large-diameter Virginia Payload Tubes and the new sonar, in particular) and some parts-quality-related issues throughout the first Flight III, the PCU North Dakota.

The problems have forced the cancellation of the planned May 2014 Commissioning–but what was really cancelled were the Alpha, or “builders” trials. You know, the ones that can lead to a Thresher-like incident.

Not good. From the news, it feels like an ugly grab-bag of issues came to a head just as the PCU North Dakota was undergoing builders trials on the 14th. That says to me that there was something materially unsound with the sub–something that would have had Admiral Rickover out hunting scalps. While it is good SUBSAFE worked, and somebody forced the trials to stop, the fact that the clock was allowed to run down to this point should make observers worry that something is out of step between production and safety.

Any way you slice this, it isn’t good. And with the Flight III serving as a foundation for a more significant design changes down the road, this is a tough break for the program.

A Black Eye For Sub Builders

101230-N-8423B-021This stands as a rare rebuff to General Dynamics Electric Boat. But before Huntington Ingalls executives start the gleeful process of using this event to chip away at General Dynamics’ dominance in undersea platforms, it might be worth remembering that the bow design change was a joint project, with design and build shared between the two companies.

It was all supposed to be a success. Twenty percent of the existing design was changed in the Flight III’s, and the changers were going to shave some $100 million bucks from the total sub cost. Stars and Stripes, in an excellent November 2013 article by Jennifer McDermott, even got Rear Adm. David C. Johnson, the program executive officer for submarines, on record in November, saying:

It shows how well Electric Boat and Newport News worked together on that, and it shows that we got the redesigns right because it did actually make the ship easier to build,” he said in an interview.

We shall see if the tight team can survive, or if it will self-destruct, just as the DDG-1000 teaming agreement did.

A Partnership In The Balance:

NNS-HIII’ve written about the sub workshare split before, and, given that HII Newport News is responsible for the stern, habitability and machinery spaces, torpedo room, sail and bow (Electric Boat–the sole Virginia Class prime–builds the engine room and control room), Newport News might be sweating some supplier issues right now.

Both yards work on the reactor plant and alternate on the final assembly, vessel test, outfit and delivery piece, so it could be that General Dynamics, charged with final assembly of the North Dakota, got stuck with some bad modules.

But material issues aside, Electric Boat apparently had a bit of trouble with the bow redesign, too. In the November article, Stars and Stripes got Kurt A. Hesch, EB’s vice president who manages the Virginia-class program, to make a revealing admission:

Historically, he said, EB has changed submarine designs to add capabilities, rather than to cut costs, and the first submarine with changes would take longer to build and would cost more. The challenge with the North Dakota, Hesch said, was “breaking that paradigm.”

In retrospect, that’s a cringe-worthy comment from an organization that normally runs a really tight PR ship. Just. Yikes.

Nobody in the Virginia Class Submarine Consortium is coming out of this a winner. Both loose. And it has a feel that somebody, somewhere took great pains to engineer the simultaneous revelation of faults with both of the two sub-builders, to help keep everybody sweet.

We’ll see how it goes.

You Can Only Squeeze So Much:

sub christeningTrouble in the Virginia Class production line was a somewhat foreseeable event. The constant drumbeat to build subs faster! For less! stops only when something in the system collapses–usually the only thing that turns things around is a catastrophic accident.

If the Virginia Program office and the head honchos running the General Dynamics Electric Boat/Huntington Ingalls Industries partnership were really foresighted, they’d have all long been busy deflecting narratives like this one articulated by Congressman Joe Courtney (D-Electric Boat) in November 2013:

EB previously delivered the USS Mississippi to the Navy in 62 months. Its shipbuilding teammate, Newport News Shipbuilding in Virginia, built the USS Minnesota in 63 months.

U.S. Rep. Joe Courtney, D-2nd District, said EB’s performance is the most powerful argument for Congress’ continued support of the program.

“It just eclipses all of the potential obstacles to getting funding for two submarines a year, because it’s a program where its performance, not its hype, is demonstrating that it’s a really solid investment for the American taxpayer,” he said.

Hesch said EB must continue to improve on its past performance, especially now that the Defense Department budget is shrinking.

But, with all the competition between the two sub-building frenemies, I can’t help but wonder if there may be fear that if one company admits stress, the other will take full advantage of the situation.

We need to be mature, and drive awareness that, at some point, you can’t get more efficient without cutting corners. And in subs, that is almost always fatal.

When Did The Problems Start?

subonedebondeddetailPeople had to know there were problems with the PCU North Dakota. You don’t have a trials-delaying issue without a good number of folks knowing many, many months ahead of time that something was wrong.

So why didn’t this all come out? Why wasn’t it fixed? Well, I expect that, in 2013, a lot of people ran out the clock, keeping production and design problems under wraps or “in house”. For better or worse, it is standard practice for troubled Programs to employ a bit of legerdemain to keep everything negative about a Program hidden away until the budget is protected and anything related (i.e., the SSBN(X)) is safe.

Now, I speculate, but there may have been signs that something wasn’t going quite right at Electric Boat back in September 2013. That is when a solid Jeff Geiger–a former surface-ship builder who, against long odds, filled the GD Bath Ironworks yard–was, after a September announcement from General Dynamics, shifted to lead Electric Boat, replacing 40-yr veteran Kevin Poitras in November (all while GD turned to another 40-yr veteran, shipbuilding king Fred Harris, to run the rest of the business).

Things were obviously slipping. General Dynamics and the Navy were, back in November, publicly planning to deliver the North Dakota in January, or, at the latest, February. From Stars and Stripes:

If the tests at sea can be done before Christmas and there are no major issues, EB will deliver the North Dakota to the Navy in January after 59 months of construction, which would be the shortest construction period yet for a Virginia-class submarine.

A February delivery also would accomplish the goal for which EB has been striving, to cut the construction time for each submarine to 60 months. EB was not expected to reach that milestone until it built the 15th member of the class, the Colorado.

“The work of the more than a thousand shipyard craftsmen and engineers who built this boat has helped make the fleet stronger and our nation safer,” Secretary of the Navy Ray Mabus said in a statement. “Their dedication and expertise has the world’s most advanced submarine on track to deliver in early 2014, giving the North Dakota the shortest construction span of any Virginia-class submarine to date.”

131102-N-UM744-003Not good. For Ray Mabus to say that back in November…it suggests either the problems were either not known, not revealed to the Navy customer, or that the scope of the problems were not fully fed up the Navy’s command chain. None of those options mean anything good.

By January, the delivery date had quietly, and with little fanfare, slipped to April or May of 2014, making a May Commissioning even more unlikely.

But the Navy just kept plowing along, as if nothing was amiss. In January, a May 2014 Commissioning date was announced, and in March, the Navy dispatched Rear Admiral Richard Breckenridge to North Dakota to drum up enthusiasm for the May commissioning.

So why the dust-up now?  Obviously, trials dates had been quietly pushed back for months, with little or no public impact. Maybe pushing the boat right up to the brink of a builders trial was the only way to really identify quality and design issues. I dunno. It never should have gotten to this point.

Admiral Rickover’s Ghost must be livid.

UPDATE–ASN(RDA) Sean Stackley must be a tad irked, too.  Here’s his April 10 Testimony to the Senate Armed Services Committee: “The next ship, North Dakota (SSN 784), fully encompasses the Design for Affordability efforts begun in 2005, which include a completely redesigned bow section, and is expected to have the shortest construction span for a VIRGINIA Class submarine.” For those of you keeping count, 62 months is the current record (USS Mississippi), and the North Dakota hit that in April.  It boggles my mind that Stackley would go on record suggesting that a sub would go through Builders Trials and Acceptance trials, AND be delivered in less than twenty days?  That’s….madness.

A Few Final Questions:

web_131102-N-SF554-046As I said before, it has been great to see Virginia Class sub builders race each other to drive down cost and schedule. But when these competitive pressures start to impact crew safety, we all need to step back, take a few deep breaths, and re-evaluate.

The Navy needs good subs, quickly. But a major accident would derail everything–and put at risk everything the Submarine community has done to become such an important–and well-funded–facet of the modern Navy.

If competitive pressure and a constant drive for efficiencies is endangering sailors or degrading the safeguards put in place to prevent another Thresher-like incident, then we have gone too far, and we must start exploring other approaches to reducing cost than those currently used by, say, Walmart.

I urge the Navy to study the design and construction of the PCU North Dakota, convening experts from outside the Virginia Program Office to help determine if, in this case, the race to become more efficient and protect the Program aversely impacted PCU North Dakota crew safety and sub quality.

If a quest for efficiency is threatening to undermine the submarine community’s longstanding focus on safety, then it is time to do some hard thinking about the way ahead.

Follow NextNavy on Twitter

View Craig Hooper's profile on LinkedIn

{ 7 comments… read them below or add one }

Gidget August 14, 2014 at 11:43 pm

the Go – Pro HD is one of the most desirable
and popular cameras on the market. This helps to monitor and identify the potential threats on the Active Directory authentication system quickly.

According to some research studies, the number one
reason why managers and executives find themselves with a stalled or underperforming career is a lack of
interpersonal skills.

Reply

defender 2 hack ios August 14, 2014 at 7:16 am

The reason this game is set apart from the rest is due to the fact
that the player can also control a “hero”. From their earliest days on the floor, coaches tell players
the defense just takes desire. Click here to
see a video slideshow of the cases included in this article plus a fun accessory that you don’t want to
miss.

Reply

Craig Hooper April 24, 2014 at 12:11 am

Bart– I worked for a relatively big shipbuilder for a bit. I know I cared, and I know folks on the floor cared. Even the people who didn’t do their job right cared, and thought they were doing the right thing. You know shipbuilding is tough, and that it’s one of the most challenging manufacturing environments out there today.

If you want to see the very best–and the very worst–in human nature, hang out in a shipyard and you’ll see it–whether it’s a Navy yard or a corporate yard, there’s no difference. Getting folks to do the job right is hard, and sometimes–even if you’re a saint of an employer and despite your best efforts and intentions, it’ll go bad.

To keep quality high, you just gotta build checks upon checks, and then check them as well. And then get somebody else to check it all as a backup. And then, and only if you’re damn lucky, at the end of the process, you’ll pass and be able to deliver the nation a good, solid and functional warship.

Reply

bart April 23, 2014 at 3:41 am

Remenber the guy Rucks who forged signatures on weld? Saying that they were inspected and he never looked at them. People that are in a civilian business is out there to make money. They do not care about quality. Big corperations do not care about safety or the well being of our sailors. It is about how much they can line their pockets with bonuses by meeting or exceeding deadlines. The navy should consider building their own ships in their shipyards. They have the capabilities but are shot down when corperate america saying they can build it faster and cheaper. This is the result of the blinders of the american debt. If navy shipyards build the ships it might take twice as long but at least we would have a quality ship. Doing so would mean that we would not be buying 2 one billion dollar submarines a year but just one submarine. It would cut down on the budget that everyone is talking about and more importantly it would be done right and would not have to worry about quality

Reply

Moose April 21, 2014 at 1:06 am

One tool I’d like to see the Navy use more is rewarding those who identify problems. Solving problems gets you credit, but being the one to raise the red flag often only gets you grief. Whoever it was at SUPSHIP Groton that pulled the handbrake to keep 784 at the pier instead of beginning trials in that state, that’s someone who needs their kudos.

A problem with saying we’re going to focus on quality even if it means sacrificing some speed is the factors which drive the focus on speed sure aren’t going away. The budgetary pressure on the Navy is only getting worse, and the Congress in particular has shown a……..lack of understanding when it comes to the fiscal challenges the Navy faces to keep the fleet at sea. Focusing on quality sure is not cheap.

Reply

Craig Hooper April 19, 2014 at 10:50 pm

Great comment.

It seems the Navy has taken great pains to present this as a problem for both houses.

But it all comes back to incentives. Reducing build time has long been paramount. Builders save a lot if the ship leaves the yard faster (overhead costs are reduced, bonuses are higher, etc.)

But quality isn’t as valued. Yes, there has been an implicit linkage of quality to build-time (with the idea being that the ship won’t leave the yard if it ain’t done right), but there are a lot of ways to “game the refs”, and put pressure on the quality guys to pass things that probably shouldn’t. It takes a real tough quality guy to stand up to a posse of screaming production execs. And it only happens once, because the offending quality guy will be out on the street pretty quick if he/she doesn’t play ball. Local SUPSHIP guys can easily get “captured” by the folks they’re regulating, as well.

It speaks to personal courage, too. In a program like Virginia, nobody wants to be “that guy” who, by stepping up and doing what is right, ruined the record-breaking production run.

Heck, 62 months is fast enough. I urge folks to consider, in this next block buy, focusing incentives on quality, and not just speed. We have the speed. Quality is where we need to think about going next.

Thoughts?

Reply

Moose April 18, 2014 at 3:53 am

While EB’s definitely on the hook for a boat in her yard, a lot of the talk I’m seeing is suggesting HII’s got an oversight problem with their subcontractors that’s a large factor in this. Gotta make sure this gets run down all the way at both shops to see who messed up and why it wasn’t caught sooner.

On the positive side, I’d much rather this is caught on the first F3 hull before trials than other options. In particular, this will (or should) make everyone extra-vigilant for trouble during the next big change to the design, which is a whopper.